皇冠彩票平台

  • <tr id='Olnnju'><strong id='Olnnju'></strong><small id='Olnnju'></small><button id='Olnnju'></button><li id='Olnnju'><noscript id='Olnnju'><big id='Olnnju'></big><dt id='Olnnju'></dt></noscript></li></tr><ol id='Olnnju'><option id='Olnnju'><table id='Olnnju'><blockquote id='Olnnju'><tbody id='Olnnju'></tbody></blockquote></table></option></ol><u id='Olnnju'></u><kbd id='Olnnju'><kbd id='Olnnju'></kbd></kbd>

    <code id='Olnnju'><strong id='Olnnju'></strong></code>

    <fieldset id='Olnnju'></fieldset>
          <span id='Olnnju'></span>

              <ins id='Olnnju'></ins>
              <acronym id='Olnnju'><em id='Olnnju'></em><td id='Olnnju'><div id='Olnnju'></div></td></acronym><address id='Olnnju'><big id='Olnnju'><big id='Olnnju'></big><legend id='Olnnju'></legend></big></address>

              <i id='Olnnju'><div id='Olnnju'><ins id='Olnnju'></ins></div></i>
              <i id='Olnnju'></i>
            1. <dl id='Olnnju'></dl>
              1. 当前位置:
                皇冠彩票平台
                >新绍兴市交通投资集团>新闻中心>媒体聚焦
                杭绍台绍兴至金华段全线开工 有套设备全省首创
                2017-08-23 15:00:13 浏览次数:

                       8月21日,全省公路水运品质工程推进会暨公路隧道施工标准化现场会在绍兴召开。本次会议为期二天,旨在通过梳理经验、分析问题,进一步推进我省公路水运“品质工程”建设,为实现“5411”综合交通发展战略提供坚强保障。省交通运输厅党组副书记、副厅长陈利幸,省交通运输厅党组成员、总工程师李志胜,绍兴市人民政府副市长丁如兴出席会议。

                  会上,绍兴市交通建设有限公司介绍的“两机一桥六台车”隧道系列施工设备引起了与会人员的关注。据介绍,该设备开创了全省公路隧道开挖、初支、防水、电缆沟等全过程机械化、流水线施工。在杭绍台3标项目平水隧道的施工中,该套设备有效防治了隧道施工质量通病、控制了施工安全风险、改善了一线人员施工作业环境、提高了施工效率。

                  杭绍台高速公路绍兴至金华段由绍兴市负责施工的道路全长115.368公里,分10个土建标,先行土建3标段于2015年11月开工,4-10标现已开工,工期为4年。目前形象进度已超过18%。在项目施工中,绍兴市交通建设有限公司提出了“品质杭绍台,美丽高速路”的全寿命建设管理理念。结合其作为典型山区高速公路的特点,该公司又细化提出了品质隧道、品质梁板、品质高墩、品质小构、品质路面、品质路基六个方面的品质创建思路,从工程建设的全过程和各环节树立品质保障。

                  据悉,作为省重点工程,杭绍台高速公路建成后,将穿越浙中腹地贫困山区,串起杭甬高速、绍诸高速、甬金高速,成为缓解、分流上三高速、甬台高速、诸永高速车流量的的一条南北大通道。

                    javascript:;  浙江在线  2017年8月22日


                  打印   关闭